THE COMPANY

History

November 2000 Incorporation of the company
January 2002 Laying the foundation stone of plant I
March 2003 Start of production with 50.000 tons/year biodiesel
August 2005 Commissioning of the extension up to 75.000 tons/year biodiesel
September 2006 Laying the foundation stone of plant II
October 2007 Commissioning of plant II with 200.000 tons/year biodiesel
August 2009 Acquisition of majority shares by PROKON Biogene Kraftstoffe GmbH
May 2010 Start of construction of plant III